CENTO calculator · DDU

Penalty for delayed handover under DDU

Estimate the Article 6 penalty under Federal Law No. 214-FZ using the contract price, deadline, and actual handover date.

Free, no registrationThe calculation is stored on this device for 30 days, and the link in the email lets you open it on another deviceOfficial sources
1

Calculate

Calculation inputs

Enter three fields to estimate the penalty for a delayed handover.

Who is claiming the penalty?

The calculation is stored in this browser for 30 days. No amount or dates are sent before you request the checklist.

Preliminary result

Your result will appear here

We will show the penalty, delay period, and key-rate period breakdown.

This informational result does not replace review of the DDU, handover act, special rules, and current restrictions.

Understand the result

%

When the right arises

The developer missed the contractual handover deadline and the participant can prove the price and dates.

What to prove

The DDU and amendments, handover deadline, contract price, handover act date, and delivery of the demand.

!

When the result changes

A moratorium, special rule, price change, deadline amendment, or disputed handover date may change the amount.

How it is calculated+

Contract price × key rate × delay days / 150 for an individual or / 300 for a legal entity or sole trader. The period is split by rate changes and calendar years.

Method and official sources

Rates verified through: 09/08/2026

Next step with CENTO

Prepare a demand to the developer

Get a demand with the chronology, penalty calculation, and evidence list for the DDU.

About the DDU penalty calculation

The penalty may arise when a developer misses the contractual handover deadline. The statutory rate is doubled to 1/150 of the Bank of Russia key rate for an individual and is 1/300 for a legal entity or sole trader. Moratoria, special rules, and disputed terms require document review.

When does a DDU penalty arise?

There must be a DDU, an expired handover deadline, and actual handover after that deadline. The agreement and handover act should support the dates and price.

Which rate applies to an individual?

An individual uses the doubled rate of 1/150 of the Bank of Russia key rate for every delay day.

Which rate applies to a legal entity or sole trader?

A legal entity or sole trader uses 1/300 of the key rate for each delay day unless a special rule applies.

Which dates should I enter?

Enter the contractual handover deadline and the actual handover date. The period runs from the next day after the deadline through the handover date.

What can change the result?

An amendment, deadline extension, price change, moratorium, special regulation, or disputed handover date can change the amount and requires document review.

Which documents support a demand?

Usually the DDU and amendments, payment records, handover act, deadline correspondence, and the demand with proof of delivery.

Penalty for delayed handover under DDU · CENTO